Gantry Crane Price Guide 2026: What MH, MG and RMG Models Actually Cost
If you are budgeting a gantry crane for a yard, precast plant, rail terminal or shipyard, the price spread between a 5-ton MH single-girder unit and a 40-ton RMG container crane is not a matter of a few percent โ it is roughly a 10x range. This guide breaks down realistic 2026 price bands by model, explains what drives the number up or down, and shows where buyers typically overspend.
Quick Reference: 2026 Gantry Crane Price Bands (FOB China)
- MH single-girder gantry, 1โ10T, 12โ30m span: USD 8,000โ28,000
- MG double-girder gantry, 5โ50T, 18โ35m span: USD 35,000โ180,000
- RMG rail-mounted container gantry, 30โ40T: USD 220,000โ650,000+
- Shipbuilding gantry (custom, 50โ300T): quoted per project, typically USD 500,000โ2,500,000
These figures assume standard Q345B steel structure, Schneider/Siemens/ABB electricals, SEW or equivalent gearboxes, and CE-level documentation. Freight, foundation, rails and installation are excluded.
MH Single-Girder Gantry: The Entry Point
The MH is the workhorse for outdoor storage yards, small precast beds and maintenance bays. Capacities run 1โ20T, but the price curve is steepest below 10T because the hoist and end-carriage assembly dominate cost.
- 3T, 15m span, CD electric hoist: USD 8,000โ13,000
- 5T, 18m span: USD 12,000โ18,000
- 10T, 22m span: USD 20,000โ28,000
Practical advice: if your duty cycle is under 15 lifts/hour and you are not handling molten metal or containers, the MH is almost always the correct financial decision. Buyers who upgrade to MG "for safety" at 5T typically spend 2.5x for capacity they never use.
MG Double-Girder Gantry: Where Most Industrial Buyers Land
The MG is the standard choice for 10โ50T outdoor lifting โ precast panels, steel coils, pipes, fabricated structures. Two girders, a trolley hoist, and a wider wheelbase give better stability and higher duty class (A5โA7).
- 10T, 20m span, A5: USD 35,000โ55,000
- 20T, 25m span, A5: USD 60,000โ95,000
- 32T, 30m span, A6: USD 95,000โ140,000
- 50T, 35m span, A7: USD 140,000โ180,000
Three cost drivers matter more than capacity itself:
- Span. Going from 20m to 30m adds roughly 25โ35% to steel weight and price. If your yard layout is flexible, shrinking span by 3โ4m is the single fastest way to cut cost.
- Duty class. A6 vs A5 adds 10โ15%; A7 adds 20โ30% through heavier motors, brakes and structure.
- Cantilever length. Each metre of cantilever on one or both sides is priced almost like main span steel.
RMG Container Gantry: Rail-Mounted, High-Cycle
RMG cranes for 20ft/40ft container handling start around USD 220,000 for a 30.5T single-container unit and climb past USD 650,000 for a 40T twin-lift with full automation, anti-sway and remote diagnostics.
- 30.5T, 6+1 wide, semi-automatic: USD 220,000โ320,000
- 40T, 7+1 wide, twin-lift: USD 380,000โ520,000
- 40T, automated stacking, remote control room: USD 520,000โ650,000+
RMG pricing is dominated by the control system, not the steel. A semi-automatic RMG and a fully automated one can share 70% of their structure and differ by USD 200,000 in drives, PLCs, laser positioning and software.
What Moves the Price Beyond the Base Quote
- Design standard. GB/T 3811 is the baseline. FEM 1.001 or DIN 15018 adds 5โ12%; CMAA #70 for North American projects adds 10โ18% due to heavier structure and documentation.
- Components. Schneider/Siemens/ABB/SEW is the standard export configuration. Substituting unbranded drives can cut 8โ15% but complicates spare parts in 3โ5 years.
- Certification. CE, EAC (TR CU 010/020), GCC/SASO, SONCAP and KEBS each require different documentation and sometimes structural re-verification. Budget USD 1,500โ6,000 per certification set.
- Environment. Outdoor coastal or foundry duty requires galvanizing, epoxy systems or IP55+ panels โ typically 6โ12% uplift.
How to Get an Accurate Number Fast
To receive a firm quote rather than a range, prepare five data points: capacity, span, lifting height, duty class, and power supply (voltage/phase/Hz). With those, a competent exporter can return a priced offer in hours, not weeks. Chunhua Crane quotes within a 4-hour SLA across its 81 standard models, with 30โ45 day production and a 12-month warranty. No MOQ applies.
For a same-day budget figure on MH, MG or RMG configurations, contact the export team at WhatsApp +86 193 9277 7259 or yuhua0095@gmail.com with your five specifications.